{"id":11043,"date":"2026-04-29T03:20:46","date_gmt":"2026-04-29T03:20:46","guid":{"rendered":"https:\/\/himalhub.com\/?p=11043"},"modified":"2026-04-29T05:46:30","modified_gmt":"2026-04-29T05:46:30","slug":"west-asian-crisis-disrupts-bitumen-supply-stalling-major-road-projects","status":"publish","type":"post","link":"https:\/\/himalhub.com\/?p=11043","title":{"rendered":"West Asian crisis disrupts bitumen supply, stalling major road projects"},"content":{"rendered":"<p style=\"text-align: justify;\" data-start=\"0\" data-end=\"351\"><strong>Himal Hub \/<\/strong> A supply shock tied to escalating tensions between the <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">United States<\/span><\/span> and <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Iran<\/span><\/span> has triggered a nationwide shortage of bitumen, paralysing asphalt works across <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Nepal<\/span><\/span> at the height of the construction season and derailing progress on several flagship road projects.<\/p>\n<p style=\"text-align: justify;\" data-start=\"353\" data-end=\"659\">Officials warn the disruption has struck at the heart of national pride and strategic infrastructure schemes, casting serious doubt on whether annual road surfacing targets can be met. While a handful of projects continue limited operations using residual stock, most have suspended asphalt works entirely.<\/p>\n<p style=\"text-align: justify;\" data-start=\"661\" data-end=\"928\">\u201cThere is a shortage of bitumen in the market, and construction material costs have also surged,\u201d said Bijay Jaisi, Director General of the Department of Roads. \u201cThis has had a sweeping impact nationwide, and discussions are under way to identify an urgent solution.\u201d<\/p>\n<p style=\"text-align: justify;\" data-start=\"930\" data-end=\"1387\">Among the hardest hit are landmark initiatives such as the <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Mid-Hill Highway<\/span><\/span>, <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Postal (Hulaki) Highway<\/span><\/span>, <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Koshi Corridor<\/span><\/span>, <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Kaligandaki Corridor<\/span><\/span>, <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Karnali Corridor<\/span><\/span>, and the <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Kathmandu-Tarai Expressway<\/span><\/span>. Asphalt operations have also stalled on major stretches including the <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Madan Bhandari Highway<\/span><\/span> and the critical Nagdhunga\u2013Mugling road section.<\/p>\n<p style=\"text-align: justify;\" data-start=\"1389\" data-end=\"1720\">The impact is particularly stark along the heavily trafficked Nagdhunga\u2013Mugling corridor, which handles more than 12,000 vehicles daily. Asphalt works have come to a standstill after existing bitumen stocks were exhausted, leaving portions of the 94.66-kilometre upgrade incomplete despite nearing final stages in several sections.<\/p>\n<p style=\"text-align: justify;\" data-start=\"1722\" data-end=\"2013\">Project officials report that in the Nagdhunga\u2013Naubise stretch, preparations for the final asphalt layer were abruptly halted, with only six kilometres completed before supplies ran dry. Elsewhere, stripped road surfaces lie exposed, raising safety concerns as the monsoon season approaches.<\/p>\n<p style=\"text-align: justify;\" data-start=\"2015\" data-end=\"2264\">Approximately 5,000 tonnes of bitumen are urgently required to resume work, according to project authorities. Progress has been further complicated by local protests delaying the extraction of construction materials, despite environmental clearance.<\/p>\n<p style=\"text-align: justify;\" data-start=\"2266\" data-end=\"2571\">The crisis extends well beyond a single project. The Koshi Corridor remains less than half complete despite repeated deadline extensions, while the Kaligandaki Corridor has crossed 80 percent but now faces delays. The Karnali Corridor lags even further behind, with barely one-fifth of the work completed.<\/p>\n<p style=\"text-align: justify;\" data-start=\"2573\" data-end=\"2964\">Ambitious long-term projects are also faltering. The Mid-Hill Highway, nearly two decades in the making, has achieved just over 80 percent completion, with this year\u2019s surfacing targets falling far short. Similarly, the Postal Highway\u2014designed to connect the Tarai belt\u2014faces mounting delays, with officials conceding that annual targets may not be met without immediate supply improvements.<\/p>\n<p style=\"text-align: justify;\" data-start=\"2966\" data-end=\"3259\">Even projects that had shown steady progress, such as the Madan Bhandari Highway, are now losing momentum. Meanwhile, the Kathmandu-Tarai Expressway, a high-priority national project being executed by the Nepali Army, has also seen its pace slow due to material shortages and escalating costs.<\/p>\n<p style=\"text-align: justify;\" data-start=\"3261\" data-end=\"3509\">Road schemes backed by international partners have not been spared. Projects under the <span class=\"hover:entity-accent entity-underline inline cursor-pointer align-baseline\"><span class=\"whitespace-normal\">Asian Development Bank<\/span><\/span>, including key expansion programmes, are experiencing similar setbacks as rising fuel prices compound supply constraints.<\/p>\n<p style=\"text-align: justify;\" data-start=\"3511\" data-end=\"3858\" data-is-last-node=\"\" data-is-only-node=\"\">Contractors say the dual pressure of bitumen scarcity and soaring petroleum costs has forced them to scale back operations nationwide. With the monsoon imminent, officials warn that unfinished roadworks could heighten the risk of landslides, disrupt traffic, and further push back already strained timelines unless supply chains stabilise swiftly.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Himal Hub \/ A supply shock tied to escalating tensions between the United States and Iran has triggered a nationwide&hellip;<\/p>\n","protected":false},"author":1,"featured_media":11046,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[6],"tags":[],"class_list":["post-11043","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-home"],"_links":{"self":[{"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/posts\/11043","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/himalhub.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=11043"}],"version-history":[{"count":1,"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/posts\/11043\/revisions"}],"predecessor-version":[{"id":11045,"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/posts\/11043\/revisions\/11045"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/himalhub.com\/index.php?rest_route=\/wp\/v2\/media\/11046"}],"wp:attachment":[{"href":"https:\/\/himalhub.com\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=11043"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/himalhub.com\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=11043"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/himalhub.com\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=11043"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}